Report on Resources

The Ministry of Finance estimates for 2005/06 were $366.6 million. During the year the Ministry received $712.7 million in additional funding for the Negotiating Framework and one-time repairs and maintenance to Government House. Total authorized estimates for the year were $1,079.3 million. At the end of 2005/06, the Ministry of Finance was under-expended by $294.9 million. The majority of the underspending in the Ministry of Finance relates to the Negotiating Framework. All agreements due March 31 were settled by March 31. Incentive funding for various agreements expiring at later dates remained unspent at March 31. Cross government Ministers' travel costs were lower due to the election held in May 2005.

Funding is provided in the Ministry Operations Vote of the legislature and one special account, Insurance and Risk Management.

The following table summarizes the budgeted and actual expenses for the Ministry for fiscal 2005/06. Variances are calculated as "Total Estimated" minus "Actual" = "Variance", so that underspending is without brackets and overspending in brackets.

Resource Summary 2005/06

Core Business Areas Estimated Other Authorizations Total Estimated Actual Variance
Operating Expenses ($000)
Crown Agencies Secretariat  1,497   1,497 1,214 283
Financial and Economic Performance and Analysis  6,415   6,415 6,116 299
Financial Governance, Accounting and Reporting  6,721   6,721 5,808 913
Treasury  1   1 1 0
Financial and Corporate Sector Services  1,565   1,565 1,392 173
Public Sector Employer's Council  14,596   14,596 14,452 144
Executive and Support Services  15,776 2,400 18,176 15,635 2,541
Contingencies (All Ministries) and New Programs  320,000        
Transfer to Ministries    (289,711) 30,289 30,000 289
Negotiating Framework Incentive    1,000,000 1,000,000 709,710 290,290
Total  366,571 712,689 1,079,260 784,328 294,932
Full-time Equivalents (FTEs)
Crown Agencies Secretariat  10   10 9 1
Financial and Economic Performance and Analysis  65   65 51 14
Financial Governance, Accounting and Reporting  117   117 108 9
Treasury  74   74 66 8
Financial and Corporate Sector Services  144   144 145 (1)
Public Sector Employer's Council  13   13 12 1
Executive and Support Services  145   145 138 7
Total  568   568 529 39
Ministry Capital Expenditures (Consolidated Revenue Fund) ($000)
Crown Agencies Secretariat  18   18 0 18
Financial and Economic Performance and Analysis  45   45 13 32
Financial Governance, Accounting and Reporting  215   215 187 28
Treasury  1,631   1,631 962 669
Financial and Corporate Sector Services  2,604   2,604 1,617 987
Public Sector Employer's Council  3   3 0 3
Executive and Support Services  1,036   1,036 45 991
Total  5,552   5,552 2,824 2,728
Insurance and Risk Management (IRMA) Estimated Other Authorizations Total Estimated Actual Variance
Operating Expenses ($000)  0   0 (7,811) 7,811
FTEs  46   46 43 3
Ministry Capital Expenditures ($000)  20   20 9 11
1  Estimates as presented to the Legislative Assembly on September 14, 2005.
2  "Other Authorizations" includes $2.4 million access to Contingencies for repairs and maintenance to Government House.