Ministry 2002/03 Annual Service Plan Report -- Government of British Columbia.
         
Contents.
Printer-friendly versionAdobe Acrobat Reader link page. (PDF)  
Message from the Minister  
Accountability Statement  
Year-at-a-Glance Highlights  
Ministry Role and Services  
Performance Reporting  
Report on Resources  
Summary Reports on Other Planning Processes  
Appendix 1 — Crown Corporations and Commissions  
Appendix 2 — Minister's Legislative Mandate  
Appendix 3 — BC Transportation Financing Authority Financial Statements  

Other Links.
Ministry of Transportation Home  
2002/03 Annual Service Plan Reports Home  
 

2002/03 Annual Service Plan Report
Ministry of Transportation

Report on Resources

2002/03 Resource Summary — Ministry of Transportation

Link to Resource Summary. Link to Resource Summary.

 

2002/03 Resource Summary — BC Transportation Financing Authority

Link to Resource Summary. Link to Resource Summary.

 

Complete BC Transportation Financing Authority Financial Statements are available in Appendix 3.


Major Capital Projects

Nisga'a Highway

Objectives:

The key component of the Nisga'a Highway project is the upgrading of the gravel resource road in the Nass Valley. The road is a vital connection between three Nisga'a communities, linking them with Terrace and the provincial highway network. The province is continuing a seven-year investment program with two components:

  • upgrading the Nisga'a Highway to an all weather two-lane highway (general 70 kilometre per hour standard) to better serve Nass Valley residents and resource industries in the area.
  • construction of the new Greenville to Kincolith road to open up access to the Village of Kincolith. This project is financed under a cost sharing partnership comprising the federal and provincial governments and the Nisga'a Tribal Council.

Costs:

  • The estimated total project cost for the Nisga'a Highway Upgrade is $52 million. Expenditures to March 31, 2003 are $25.1 million.
  • The estimated total project cost for Greenville-Kincolith Road (new route) is $34.6 million ($17.5 million provincial share). Expenditures to March 31, 2003 are $32.5 million.

Benefits:

  • Safety, access and mobility improvements.
  • Increased economic development (e.g. tourism).

Risks:

  • Technical and financial risks. The Greenville to Kincolith route traverses some very rugged terrain, including sections where high cliffs drop sharply to the Nass River. The project presents numerous engineering and construction challenges.

Kicking Horse Canyon

Objectives:

The improvement program for the Kicking Horse Canyon involves upgrading the 26-kilometer section of the Trans Canada Highway between Golden at the junction of Highway 95 and the western boundary of Yoho National Park to a modern four-lane standard. This investment would represent a major service improvement to the Trans Canada Highway and is directed at:

  • responding to continual and severe safety problems;
  • minimizing road closures due to slides and accidents;
  • replacing of two major structures that are nearing the end of their service lives;
  • supporting the efficient movement of goods and services;
  • facilitating trade and commerce;
  • supporting tourism and associated local business opportunities; and
  • augmenting the capacity of a critical provincial/national gateway.

Costs:

The estimated capital cost of the improvement program is $730 million. The upgrade will proceed in three phases:

  • 5-Mile (Yoho) Bridge ($61 million). This work is being cost shared with the Government of Canada under the Strategic Highway Infrastructure Program (SHIP): $23 million federal and $38 million provincial. Construction is in progress and expenditures to March 31, 2003 are $19.2 million. Construction of this section is on target and is expected to be completed by fall 2006.
  • 10-Mile (Park) Bridge ($130 million). This work is being cost shared with the Government of Canada under the Strategic Infrastructure Fund (SIF): $62.5 million federal and $67.5 million provincial. Construction is in progress and expenditures to March 31, 2003 are $2.3 million. Financing and project delivery options through a public-private partnership are being investigated.
  • Golden to 5-Mile and 10-Mile to Yoho National Park. The estimated total cost of constructing these two sections and final third phase is $539 million. The federal government had made no commitment to cost sharing on this section as of the end of 2002/03.

Benefits:

  • The net present value of the 5-Mile (Yoho) Bridge and 10-Mile (Park Bridge) sections is $110 million based on safety, travel time, reliability and economic development benefits.

Risks:

  • Technical Risk: Rock and slope stability and climatic conditions.
  • Financial Risk: Possible construction problems due to difficult topography and material costs.
  • Uncertainty around ongoing availability of federal funding.

Okanagan Lake Bridge

Objectives:

  • Construct a new four lane bridge (expandable to five lanes) to reduce congestion in peak hours and through the summer. Includes construction of a couplet system in downtown Kelowna to improve traffic flow and the addition of a truck climbing lane on the west side of Okanagan Lake.
  • Reduce travel time from the South to the Central Okanagan and facilitate tourism, goods movement and business travel.

Costs:

  • The estimated total cost of the project is $100 million. Financing and project delivery options through a public private partnership are being investigated.
  • Expenditures to March 31, 2003 are $7.6 million for the project development and design.

Benefits:

  • The net present value of the benefits of the project is $109.1 million, and includes improved safety, travel time savings and economic development.

Risks:

  • Technical Risk: The risks associated with the construction of floating bridges have been substantially reduced in recent years with the introduction of new flotation technologies.
  • Financial Risk: Possible construction problems due to engineering challenges.
  • Schedule Risk: The delivery of the project through the P3 process may delay the initial construction of the bridge.

Sea-to-Sky Highway

Objectives:

The Sea-to-Sky Highway Upgrade is part of a long-term corridor improvement needs project. It involves critical safety improvements to Highway 99 (Sea-to-Sky), and lane expansions along certain sections of the highway between Horseshoe Bay and Whistler. The upgrade addresses continual and severe safety and mobility concerns, will reduce road closures due to slides and accidents, and at the same time will meet the requirements of the 2010 Olympic Bid.

Costs:

  • The estimated project cost is $600 million, and expenditures to March 31, 2003 are $10.4 million related to environmental studies, geotechnical investigations, financing and procurement strategies, traffic management planning, consultation with stakeholders, and technical support for the 2010 Olympic bid.

Benefits:

  • The estimated value of user benefits over the period 2010 to 2025 is $873 million, and includes travel time savings, operating and accident cost savings.

Risks:

  • Technical Risk: Rock and slope instability and climatic conditions.
  • Financial Risk: Possible construction problems due to difficult topography and material costs.

Lions Gate Bridge

Photograph -- Lions Gate Bridge.

Objectives:

  • Replace the aging bridge deck to reduce maintenance costs and eliminate the possibility of deck failure.
  • Create a safer and more efficient route for motor vehicles, cyclists and pedestrians.

Costs:

  • The project budget was $125 million. Expenditures to March 31, 2003 are $124 million. The project was completed during 2002/03.

Benefits:

  • Increased safety and extended useful life of the bridge.

Risks:

  • Risks became negligible with project completion.

Vancouver Island Highway

Objectives:

  • Provide a transportation corridor that addresses the needs of Vancouver Island residents, visitors and the economy, and improves safety.

Costs:

  • The project budget was $1.3 billion, and expenditures for the 2002/03 fiscal year were $30.6 million. The project was formally initiated in 1993/94, and is now complete with total expenditures to March 31, 2003 of $1.3 billion.

Benefits:

  • Benefits include time savings, reductions in the number of traffic accidents of up to 60 per cent in some sections, and reduced vehicle operating costs.

Risks:

  • Risks became negligible with project completion.

 

 
Home -- 2002/03 Annual Service Plan Reports.
Previous. Next.
Feedback. Privacy. Disclaimer. Copyright. Top. Government of British Columbia.