 |
 |
2005/06 – 2007/08 SERVICE PLAN
Ministry of Transportation
Resource Summary
Ministry of Transportation
Core Businesses |
2004/05 Restated Estimates1 |
2005/06 Estimates |
2006/07 Plan |
2007/08 Plan |
Operating Expenses ($000) |
Transportation Improvements2 |
12,623 |
12,651 |
12,651 |
12,559 |
Public Transportation3 |
363,474 |
359,292 |
363,826 |
361,329 |
Highway Operations |
414,902 |
419,006 |
415,030 |
418,129 |
Passenger Transportation Regulation |
1,767 |
2,301 |
2,243 |
2,243 |
Executive and Support Services |
11,689 |
11,695 |
11,695 |
11,695 |
Total |
804,455 |
804,945 |
805,445 |
805,955 |
Full-time Equivalents (Direct FTEs) |
Transportation Improvements |
273 |
285 |
285 |
285 |
Highway Operations |
633 |
691 |
691 |
691 |
Passenger Transportation Regulation |
20 |
22 |
22 |
22 |
Executive and Support Services |
72 |
76 |
76 |
76 |
Total |
998 |
1,074 |
1,074 |
1,074 |
Ministry Capital Expenditures (Consolidated Revenue Fund) ($000) |
Transportation Improvements |
473 |
1,255 |
1,135 |
765 |
Highway Operations |
11,285 |
14,824 |
5,918 |
2,495 |
Passenger Transportation Regulation |
0 |
183 |
179 |
184 |
Executive and Support Services |
1,522 |
383 |
130 |
539 |
Total |
13,280 |
16,645 |
7,362 |
3,983 |
Other Financing Transactions ($000) |
Receipts |
— |
— |
— |
— |
Disbursements — Public Transportation4 |
25,200 |
24,800 |
17,500 |
6,100 |
Net Cash Source (Requirement) |
(25,200) |
(24,800) |
(17,500) |
(6,100) |
Revenue ($000) |
Total Receipts5 |
77,838 |
56,951 |
58,081 |
59,301 |
BC Transportation Financing Authority — Income Statement
|
2004/05 Budget1 |
2005/06 Budget |
2006/07 Plan |
2007/08 Plan |
Revenue ($000) |
Dedicated taxes2 |
425,280 |
450,100 |
463,700 |
477,300 |
Transfer payments3 |
750,000 |
— |
— |
— |
Amortization of deferred contributions4 |
171,145 |
165,270 |
155,282 |
145,456 |
Other revenue5 |
4,844 |
18,844 |
10,844 |
10,844 |
Total |
1,351,269 |
634,214 |
629,826 |
633,600 |
Expenditures ($000) |
Amortization |
301,827 |
307,447 |
313,449 |
318,991 |
Interest6 |
150,357 |
136,743 |
156,609 |
180,599 |
Heartlands roads program7 |
35,000 |
35,000 |
35,000 |
35,000 |
Grant programs8 |
76,300 |
102,000 |
18,000 |
136,000 |
Operations and administration |
8,156 |
3,866 |
3,866 |
3,866 |
Total |
571,640 |
585,056 |
526,924 |
674,456 |
Net Income (Loss) ($000) |
Net Earnings (Loss) |
779,629 |
49,158 |
102,902 |
(40,856) |
Capital Plan ($000)9 |
Transportation Improvements |
533,968 |
519,552 |
602,156 |
509,352 |
Rapid Transit Project 2000 — Income Statement
|
2004/05 Budget |
2005/06 Budget |
2006/07 Plan |
2007/08 Plan |
Revenue ($000) |
Recognition of deferred capital and pre-operating contributions(1) |
28,384 |
29,348 |
28,666 |
28,027 |
Expenditures ($000) |
Amortization of deferred capital contribution(2) |
28,384 |
29,348 |
28,666 |
28,027 |
Net Income (Loss) ($000) |
Net Earnings |
— |
— |
— |
— |
Major Capital Projects
Nisga'a Highway
Objective: The Nisga'a Highway Project is in the final year of a seven-year investment program that involves upgrading the Nisga'a Highway from a gravel resource road to an all-weather, two-lane highway that meets a 70 kilometres per hour standard. The upgrade is now 75 per cent complete and is expected to be finished by the Fall of 2005. The upgrade will better serve Nass Valley residents and resource industries in the area.
Costs: The estimated total cost for the seven-year program is $52 million.
Benefits:
- Safer roads.
- Travel time savings.
- Better access to British Columbia communities.
- Economic development through increased tourism and more efficient movement of goods and services.
Risks: This project has presented engineering and construction challenges due to the rugged terrain. However, few risks remain as the construction left on the Nisga'a Highway upgrade is straightforward gravel and paving work.
Kicking Horse Canyon
Objective: Upgrade the 25-kilometre section of the Trans-Canada Highway to a modern, four-lane standard from the junction of Highway 95 at Golden to the western boundary of Yoho National Park. This corridor was originally constructed throughout the 1950s and is mostly two lanes wide. It is an important route for tourism and interprovincial trade, serving as a gateway between British Columbia and the rest of North America. Additionally, by connecting remote resource extraction sites with processing, manufacturing and distribution centres, this portion of the Trans-Canada Highway is a key part of our province's resource economies, particularly forestry and mining.
The Kicking Horse Canyon project has three phases, of which only the first two are funded and underway.
Costs: The estimated cost is $191 million for the first two phases.
- Yoho (5-Mile) Bridge (current budget $61 million): The cost of this work is being shared with the Government of Canada under the Strategic Highway Infrastructure Program (SHIP). The federal portion is $23 million and the provincial portion is $38 million. Construction is on schedule and expected to be complete by Fall 2006.
- Park (10-Mile) Bridge (preliminary estimate $130 million): The cost of this work is being shared with the Government of Canada under the Canadian Strategic Infrastructure Fund (CSIF). The federal portion is $62.5 million and the provincial portion is $67.5 million. The provincial government is pursuing private-public partnership delivery. A request for proposals was issued in October 2004.
Note: It is anticipated that in the future there will be a third phase for upgrades from Golden to 5-Mile and 10-Mile to Yoho National Park when federal cost-sharing is secured. Improvements likely will be made over the longer term, rather than within the three-year scope of this service plan.
Benefits:
- Safer roads and increased capacity on a critical provincial and national gateway.
- Fewer road closures due to slides and accidents.
- Replacement of two major structures that are nearing the end of their service lives.
- Economic development through increased tourism and more efficient movement of goods and services.
Risks:
- Challenging climatic and geographic conditions.
- Managing traffic during construction.
Okanagan Lake Crossing
Objectives: To construct a new five-lane crossing to replace the existing 46-year-old crossing which is now at the end of its economic and useful life, and to reduce the increasing traffic congestion. The project includes improvements to the east approach through downtown Kelowna to improve traffic flow, a truck climbing lane on the west side of Okanagan Lake, and an interchange at Campbell Road on the west side of the crossing.
Costs: The crossing and east approach improvements are estimated to cost $100 million. Improvements to the west approach are estimated to cost an additional $20 million. The new crossing will be delivered through a public-private partnership. The east and west approach works will be delivered through traditional tender.
Benefits:
- Safer crossing and connecting roads.
- Travel time savings due to relieved congestion.
- Economic development through increased tourism and more efficient movement of goods and services.
Risks: Engineering and construction challenges, which are substantially transferred to the private sector through the public-private partnership.
Sea-to-Sky Highway
Objectives: Implement critical safety, reliability and capacity upgrades to Highway 99 (the Sea-to-Sky Highway) by constructing lane expansions along some sections of the highway between Horseshoe Bay and Whistler. The schedule requires these upgrades to be completed by the end of 2009. Much of the design and construction will be done by a private sector partner. These upgrades are in addition to improvements currently under construction between Culliton Creek and Cheakamus Canyon.
Costs: The estimated construction cost is $600 million. Further information including a Capital Project Plan is available at http://www.seatoskyimprovements.ca/.
Benefits:
- A safer road.
- Increased capacity.
- Travel time savings.
- Reduced vehicle operating costs.
- Fewer road closures due to slides and accidents.
Risks:
- Challenging climatic conditions.
- Challenging construction due to difficult terrain or unstable areas, and the need to maintain traffic flows.
Rapid Transit Project 2000
Objective: The Millennium Line project, which is mostly complete and is running smoothly, included construction of the 21.6 kilometre Millennium Line extension to the SkyTrain rail transit system in the Lower Mainland, plus feasibility studies of two planned further extensions of SkyTrain. Construction is underway on the last portion from Commercial Station to Vancouver Community College.
Costs: The total cost of the Millennium Line is forecast to be $1.12 billion, which is lower than its approved budget of $1.17 billion. An operating lease with TransLink is in the final negotiation stage.
Benefits:
- Rapid transit service for current and future commuters.
- Reduced congestion.
- Reduced pollution from automobile exhaust emissions.
- Slower growth in the demand for new highway infrastructure.
- Less urban sprawl, due to compact development around transit stations.
Risks: Risks are related to one remaining section, from Commercial Station to Vancouver Community College, which faces standard construction and financial risks and is expected to be turned over to the operator in late 2005.
Transportation Investment Plan
The first phase of a multi-year Transportation Investment Plan for British Columbia was announced in February 2003. The Plan is set out in detail in "Opening up BC", available online at http://www.gov.bc.ca/bcgov/content/images/transportation_plan_web.pdf.
Key components of the plan include:
- Border Crossing Program — Enhancing the free flow of goods approaching and through B.C.'s busiest border crossings (highways #10, #11 (Sumas Way), #15 (176 Street), #91 and #91A), $242 million will be committed to infrastructure and technology improvements. British Columbia and provincial partners will provide $140 million, to be combined with $102 million from the federal government's Strategic Highway Infrastructure Program and Border Infrastructure Fund. This program's planned investments extend beyond the three-year scope of this service plan.
- Gateway Program — Potential projects to improve the movement of people and goods in the Lower Mainland include twinning the Port Mann Bridge and widening Highway 1 between Vancouver and Langley; developing a four-lane, 80 kilometres per hour South Fraser Perimeter Road from Tsawwassen to the Port Kells area; and improving existing roads from New Westminster through Coquitlam, Port Coquitlam and Pitt Meadows to Maple Ridge to create a North Fraser Perimeter Road. Preliminary estimates suggest this program would cost $2.6 billion. Consultation with local governments continued through 2004. The ministry is committed to work with local governments, residents, businesses and other stakeholders as the program progresses.
 |
 |
|
Port Mann Bridge |
- Highway Corridors — Improving the performance of highway corridors through projects such as passing lanes, four-laning, left turn slots and realignments. Projected investment from 2005/06 to 2007/08 is $202 million. Approximately $10 million of this will be provided by the federal government under the Strategic Highway Program.
- Highway Rehabilitation — Investing $438 million over three years (2005/06 through 2007/08) in road and bridge surfacing, bridge rehabilitation, seismic retrofits and highway safety improvements.
- Heartlands Roads — Making Heartlands roads safer and more reliable, and improving connections between communities, the ministry is investing $225 million from 2005/06 through 2007/08 to renew the northern and rural road network.
- Okanagan Corridor Improvements — Apart from a new Okanagan Lake Crossing, $60 million is expected to be invested to support trade and tourism and reduce congestion in urban areas.
- Transportation Partnerships Program — Along with contributions from partners, the ministry is reserving $10 million a year, primarily for port and airport infrastructure improvements that will bring benefits for regional economies. A portion of this program funding is directed to cost-sharing on community cycling infrastructure.
 |
 |
|
Port improvements benefit the economy |
- Weigh Scales Upgrade Program — Over the two years of 2005/06 and 2006/07, an estimated $10 million will be invested to relocate and redesign weigh scales, implement joint facility operations at borders and develop intelligent transportation systems to process truck traffic more efficiently.
- Heartlands Oil and Gas Road Rehabilitation Strategy — In partnership with the Ministry of Energy and Mines, the program will rehabilitate the existing public road infrastructure in the Northeast region of the province to help eliminate seasonal road restrictions and extend the winter drilling season for oil and gas exploration.
- Richmond-Airport-Vancouver Rapid Transit Project (RAV) — The RAV project is a jointly funded (B.C. Government, Vancouver International Airport, Federal Government and the Greater Vancouver Transportation Authority (GVTA)) rail-based rapid transit line that will link central Richmond, the Vancouver International Airport and Vancouver's downtown business district. The project is deliverable by the GVTA through its subsidiary RAVCO. The province is committed to make $435 million in contributions.
|