Performance Reporting
Report on Results
Goal 1: Efficient and Effective Delivery of Environmental
Assessment
This goal was met through two objectives: continual improvement
of provincial environmental assessment and greater procedural certainty
when both the provincial and federal CEAA review processes are involved.
Objective 1: Continual Improvement of Provincial Environmental
Assessment
Improvements to environmental assessment are ongoing. Most recently,
reforms to the Act have streamlined and improved the process by
making it less prescriptive and more flexible.
Key Strategies
- Timely and cost efficient delivery of the provincial environmental
assessment process;
- Evaluation of the environmental assessment process and development
of refinements based on implementation experience;
- Alignment of environmental assessment and permitting/licensing;
- Fulfillment of government's legal obligations towards First
Nations; and
- Facilitating proponents' and review participants' understanding
of relationship-building with First Nations.
Performance Measures and Results
1. Success meeting timelines
One key objective of environmental assessment is timeliness and
process certainty. The British Columbia process has legislated
timelines and the Environmental Assessment Office monitors whether
these timelines are being met. Early in the review, a schedule is
prepared that shows the major milestones and targets. The Environmental
Assessment Office is proactive at anticipating and scheduling activities
and encouraging effort, for example consultation during the pre-application
stage, to ensure that projects stay on track to meet schedules and
stay within legislated timelines.
Performance
Measure |
2003/04
Target |
2003/04
Actual |
Variance |
Duration of government application review |
90% of application reviews completed in 180 days |
75% of application reviews completed in 180 days |
One project did not meet the timeline for reasons discussed
below |
Reviews of the Coursier Dam Decommissioning, Eagle Rock Quarry,
and the Prince George Groundwater Projects were completed within
the legislated timeline of 180 days. The Environmental Assessment
Office Executive Director issued two timeline extensions for the
Vancouver Island Energy Corporation (VIEC) which caused the Vancouver
Island Generation project review to exceed the 180-day timeline.
Both timeline extensions were related to the concurrent British
Columbia Utilities Commission (BCUC) hearing into VIEC's application
for a Certificate of Public Convenience and Necessity. The Environmental
Assessment Office needed time to consider the implications of the
BCUC decision before referring VIEC's application for an Environmental
Assessment Certificate to Ministers, hence the delay in concluding
the environmental assessment review.
Several proponents have expressed interest in the new broader concurrent
permitting provisions which can be effective in aligning environmental
assessment and provincial permitting and licensing requirements.
Most power project proponents are considering concurrent permitting
of Water Act and Land Act tenure applications, and
in 2003, a proponent for an aggregate quarry requested concurrent
processing of permit applications. As a result, the quarry was granted
a Mines Act permit within 7 days of the environmental assessment
certificate being issued. Early experience with concurrent permitting
suggests that this could become a highly valued feature of the new
Act where applicable. For example, concurrent permitting is
easier to arrange for more straightforward projects, such as aggregate
mines, but may be a less attractive option for proponents of complex
major mines (e.g., where the mine plan is rapidly evolving).
To assist the Environmental Assessment Office with understanding
First Nations concerns and issues with environmental assessment,
the Environmental Assessment Office set up the First Nations Environmental
Assessment Working Group (FNEAWG) with representation from several
First Nations. During the 2003/04 period, FNEAWG was responsible
for preparing a First Nations Environmental Assessment Tool Kit,
a guide to environmental assessment from the perspective of First
Nations. It is expected that this guide will facilitate a better
understanding of environmental assessment and help improve working
relationships with First Nations communities on project reviews.
2. Participants' perceptions of a professional, expert, fair
and open review process
The Environmental Assessment Office relies on surveys of review
participants to provide feedback on the environmental assessment
process to determine where improvements are needed.
Performance Measure |
2002/03
Base data |
2003/04 Target |
2003/04
Actual |
Variance |
Participants' perceptions of a professional, expert, fair,
and open review process |
Proponent, First Nations and review participant survey
conducted |
Proponents:
Continual Improvement.
Others:
Maintain or improve
|
The EAO is in the process of reviewing the results of the
2004 client survey and identifying areas for improvement that
will be reported in the 2004/05 Service Plan Report |
To be evaluated when data are available |
The findings of the Environmental Assessment Office Client Satisfaction
Survey (2004) conducted from April 19, 2004 to May 6, 2004 are being
reviewed to identify areas for improvement that will be reported
in the 2004/05 Service Plan Report.
3. Costs per Project Under Review
During Core Services Review it was estimated that the costs to
government in conducting environmental assessment reviews could
be reduced by one-third, without a significant reduction in the
number of projects that are subject to review and with no reduction
in review quality. The number of reviewable projects has more than
doubled compared to levels expected during Core Services Review.
Performance Measure |
2002/03
Base data |
2003/04 Target |
2003/04
Actual |
2003/04 Variance |
Average annual government costs per project for environmental
assessment |
Estimated to be $317K. Average Annual government costs
per project confirmed as $317K. The equivalent estimated average
annual costs per project for the EAO is $265K. |
Reduce 2002/03 level of costs per project by 5%. |
The average annual EAO project cost is $106,000 which is
down from $131,000 in 2002/03. The average annual project
cost for 2003/04 ($106,000) exceeds both the 5 per cent and
the 10 per cent target reductions for 2003/04 and 2004/05
respectively. |
Target exceeded. No variance. |
This performance measure was changed in the 2004/05 Environmental
Assessment Office Service Plan to reflect average annual Environmental
Assessment Office costs per project for environmental assessment
instead of average annual government costs since Environmental Assessment
Office costs are a more meaningful measure of output and more accurate.
The 2002/03 base data was recalculated to reflect Environmental
Assessment Office costs to allow comparisons with current and future
years.
The average annual Environmental Assessment Office cost per project
for 2003/04 ($106K) exceeds both the 5 per cent and 10 per cent
targets for 2003/04 and 2004/05 respectively.
4. Reducing unnecessary red tape and regulation
The Government of British Columbia is committed to reducing unnecessary
red tape and regulation by one-third within three years. The Environmental
Assessment Office set a target of 33 per cent reduction
for fiscal year 2004/05.
Performance Measure |
2002/03
Base Data |
2003/04
Target |
2003/04
Actual |
2003/04 Variance |
Deregulation: reducing unnecessary red tape and regulation
|
56% reduction in regulatory requirements of provincial
environmental assessment |
Maintain or reduce regulatory requirements of provincial
environmental assessments |
56% reduction in regulatory requirements of provincial
environmental assessments maintained |
Target exceeded and maintained. No variance |
In 2002/03 the Environmental Assessment Office reduced regulations
by 56% from the previous year which more than exceeded the target
for 2004/05.
Objective 2: Enhance federal/provincial cooperation
to increase timeliness and certainty and minimize overlap and duplication
When a project is subject to both CEAA and the Act, the Environmental
Assessment Office works closely with the Canadian Environmental
Assessment Agency and other federal agencies to ensure the requirements
of both levels of government are met through a harmonized process.
Under the Canada-British Columbia Agreement on Environmental Assessment
Cooperation (2004), the requirements of both processes are met through
coordinated assessments to minimize overlap and duplication. Work
plans, signed off by the Environmental Assessment Office and the
Canadian Environmental Assessment Agency are developed for each
project requiring a harmonized review. Work plans set out project-specific
procedures for completing a harmonized review, which includes determining
the scope of project, scope of assessment and project review schedule.
Key Strategies:
- Implement operational processes (work plans, dispute resolution
mechanisms) to facilitate federal/provincial cooperation; and
- Negotiate a new federal/provincial agreement for environmental
assessment cooperation.
5. Harmonized Intergovernmental Review
Performance
Measure |
2002/03
Base Data |
2003/04
Target |
2003/04
Actual |
Variance |
Participants' perceptions of efforts made to achieve a
harmonized intergovernmental review |
Proponent, First Nations and review participants survey
conducted |
Proponents: Continual improvement.
Others: Maintain or improve
|
The EAO is reviewing the results of the 2004 client survey
and identifying areas for improvement that will be reported
in the 2004/05 Service Plan Report |
To be evaluated when data are available |
The findings of the Environmental Assessment Office Client Satisfaction
Survey (2004) conducted from April 19 to May 6, 2004 are being reviewed
to identify areas for improvement that will be reported in the 2004/05
Service Plan Report.
Strategies completed or underway to improve harmonized intergovernmental
reviews.
When a project is subject to both CEAA as well as the Act, the
purpose of coordinated assessments is to minimize duplication and
overlap and ensure timely reviews. In March 2004, the governments
of Canada and British Columbia approved the Canada-British Columbia
Agreement on Environmental Assessment Cooperation (2004). This agreement
reflects the amendments to CEAA and changes to the Act. Amendments
included in the 2004 agreement improve and update the earlier agreement
first completed in 1997:
- A recognition that work planning will be approached on a project-by-project
basis, so that provincial timelines are more likely to be achieved
by both levels of government;
- A dispute resolution mechanism was incorporated to involve senior-level
officials from both governments in cooperating to resolve policy
and process disputes. There is now a provision to allow third
party intervention to resolve issues, if both parties agree; and
- The recently introduced role of the Federal Environmental Assessment
Coordinator is included in the agreement as an improvement to
managing federal participation in cooperative reviews.
The Environmental Assessment Office and the Canadian Environmental
Assessment Agency are developing operational procedures where CEAA
screening level reviews and the Act reviews are being conducted
jointly. These procedures are designed to:
- Facilitate implementation of the Canada-British Columbia Agreement
on Environmental Assessment Cooperation (2004) by providing guidance
and establishing procedures for notification, establishing common
information requirements, developing project work plans and coordinating
decision-making during cooperative reviews;
- Clarify how key steps and decision points under CEAA and the
Act will be managed during cooperative assessments so that both
parties are able to meet their legislative and policy requirements;
and
- Promote consistency in the interpretation and implementation
of the agreement.
|