Performance Reporting — Continued
Goal 1: Efficient and Effective Delivery of Environmental Assessment
1) Success Meeting Timelines
Reviews of the Silverberry Secure Landfill Project, the
Burnaby Lake Rejuvenation Project, and the Stewart Bulk
Terminals Wharf Expansion Project were completed on time.
The proponent agreed to a timeline extension to complete the Basal
Aquifer Dewatering Project review. A timeline extension was
also required to complete the Forrest Kerr Hydroelectric Project
review. Both timeline extensions were issued at the request of
the Environmental Assessment Office to provide sufficient time
to resolve outstanding issues raised by First Nations and government
agencies.
Performance
Measure |
2001/02 Actual |
2002/03 Target |
2002/03 Actual |
2002/03 Variance |
Success meeting timelines
(percentage of reviews completed on time)
|
67% |
80% |
80% |
— |
In future years, this performance measure will be modified to
better reflect the new legislated requirement for government review
of project applications to be completed in 180 days or less.
The performance target for 2003/04 is for 90% of application reviews
to be completed within 180 days.
2) Participants' Perceptions of a Professional, Expert, Fair
and Open Review Process
Exit Surveys on Organizational Performance
A major performance measure for the Environmental Assessment
Office Performance Plan 2001/02 to 2003/04, as well as for the
Environmental Assessment Office Service Plan 2002/03 to 2004/05,
is the assessment of review participants' perceptions of an expert,
fair and open review process under the Act.
Performance
Measure |
2002/03
Target |
2002/03
Actual |
2002/03 Variance |
Participants' perceptions of a professional,
expert, fair, and open review process |
Proponents: continual improvement
Others: maintain or improve
|
Proponents: continual improvement
Others: improve
|
— |
The Environmental Assessment Office commissioned two separate
but complementary modes of performance surveys designed to gauge
stakeholder perceptions. Face-to-face interviews with proponents
were conducted by an outside consultant to gather information
and advice from proponents. A web-based survey managed by BC Stats
was used to collect stakeholders' input on a variety of aspects
of organizational performance. An overview of findings of both
surveys is reported below.
Feedback from Proponents
Proponents were interviewed from the four project reviews that
were completed in 2002/03: the Basal Aquifer Dewatering Project,
the Burnaby Lake Rejuvenation Project, the Silverberry
Secure Landfill Project, and an amendment to the Brilliant
Powerplant Expansion Project. The proponents generally gave
the Environmental Assessment Office (EAO) a positive report as
described below:
EAO Aspect |
Proponent comments |
Organizational Capacity |
- EAO has competent staff, capable of implementing the
environmental assessment review requirements;
- EAO dedicates sufficient organizational resources to
conducting environmental assessment reviews, although
there was indication that proponents wanted better advice
on consultation with First Nations;
- EAO makes effective use of communications technology,
however some concerns were raised over the range of correspondence
(e.g., informal emails) placed on the website;
- EAO consistently meets established review times although
questions were raised regarding the need to review certain
types of projects.
|
Delivery of an Expert, Fair and Open
Review Process |
EAO effectively communicates the environmental
assessment program.
EAO develops and implements an e-Registry that supports
a focus on client service.
EAO improves the content of Internet and Intranet sites.
|
EAO Aspect |
Proponent comments |
Support for Informed Decision-making |
- EAO ensures that reviews focus on key strategic-level
issues;
- EAO develops comprehensive and balanced reports that
accurately reflect the issues considered during the review
process;
- EAO ensures that sufficient rationale is provided for
government's environmental assessment decisions and conditions
that may be attached to certification approvals;
- EAO addresses potential impact issues by defining impact
mitigation measures where appropriate.
|
Based on the responses, the consultant who conducted the interviews
provided the following observations:
- Process costs to proponents need to be taken into consideration
during reviews. Two proponents identified situations where they
felt that the EAO established excessive public consultation
requirements. With the new EAO process in place that involves
customization of environmental assessment requirements based
on the specifics of individual projects, the EAO will be called
on to apply discretion in defining public consultation, and
other process requirements.
- Continuing efforts to improve federal/provincial environmental
assessment review harmonization appear to be needed, particularly
in respect to the requirements of Fisheries and Oceans Canada
during a joint review.
- Two proponents questioned the need to conduct environmental
assessment on their projects because, in their view, the project
did not pose significant adverse environmental threats. With
the powers under the new Act to waive out some projects, criteria
will be needed for making this determination.
- Two proponents experienced some challenges with First Nations
consultation and believe that the EAO could improve its advice
to proponents in this area.
- The EAO should continue to try to achieve close linkages between
the environmental assessment review and permitting to facilitate
the resolution of key issues that might be expected to arise
during post-certification permitting activities.
Results of stakeholder surveys (conducted by BCSTATS)
BCSTATS conducted a survey of review participants in February
and March 2003, who had been involved in at least one of nine
projects that were either completed or under active review during
the fiscal year of 2002/03. The objective of the survey was to
receive input on participant perceptions of: the capacity of the
EAO to deliver an expert, fair and open review process; the accessibility
of project review information; and the efforts to achieve harmonized
intergovernmental review.
Respondents were approached by email, phone, and postal mail
and were invited to complete the survey through a phone interview
or online. Survey participants fell into four participant categories:
proponents (including their consultants who worked on the project
review documentation); government agencies that participated in
the review (provincial, federal and local government); First Nations;
and the public (those who submitted comments, made enquiries,
or attended meetings).
The survey population consisted of 625 people of whom 163 submitted
surveys, yielding an overall response rate of 26%. The findings
indicated a relatively high perception of the administration of
the environmental assessment process by the EAO, with the highest
ratings in the area of cooperation between federal and provincial
agencies.
EAO Aspect |
Survey response (% of satisfaction
ratings "high" or "somewhat high") |
Cooperation among federal and provincial
agencies |
93% |
Communication during reviews |
89% |
Opportunities for input during the review |
82% |
Leadership in administering the environmental
assessment process1 |
80% |
Accessibility of information on project
reviews |
80% |
Level of technical expertise and analysis |
78% |
Management of the project review |
76% |
Demonstration of impartiality in administering
the process |
69% |
Comparisons across respondent types showed the greatest level
of satisfaction among proponents, followed by review agencies
with the public having less but still a high per cent reporting
satisfaction with the process. The following results for perceptions
of leadership provide an example of this trend.
EAO Aspect: Leadership
in administering the environmental assessment process |
Participant Type |
"High" or "Somewhat high" |
Neutral |
"Somewhat low" or "low" |
Proponents |
100% |
0% |
0% |
Government Agencies |
85% |
13% |
2% |
Public |
68% |
22% |
11% |
3) Cost Per Project Under Review
Upon full implementation of the new environmental assessment
process, it was estimated that the costs to government could be
reduced by about one-third, without significant reduction in the
number of projects that are subject to review and with no reduction
in review quality. In 2002/03, it is estimated that there were
15 "review years" over the 19 projects that were subject to some
level of EA review. Assuming 75% of review costs are borne by
the Environmental Assessment Office and an additional 25% of review
costs are provided by line ministries involved in the review process,
it is estimated that the average annual government environmental
assessment costs was $315K per project.
Performance
Measure |
2001/02 Actual |
2002/03 Target |
2002/03 Actual |
2002/03 Variance |
Cost per project under review
(average annual government EA costs)
|
$317K |
$317K |
$315K |
-$2K |
4) Approved plan for Cooperative Federal/Provincial Relationship
to Guide Joint Reviews
An interim extension to the Canada-British Columbia Agreement
for Environmental Assessment Cooperation was completed in 2002/03.
This extension incorporated federal-provincial work planning on
a project-by-project basis (so that the provincial timelines can
be achieved by both levels of government), as well as a dispute
resolution mechanism to involve senior-level provincial and federal
officials in cooperatively resolving policy and process disputes.
An improved long term agreement for federal/provincial cooperation
in environmental assessment continues to be a priority.
Performance
Measure |
2001/02 Actual |
2002/03 Target |
2002/03 Actual |
2002/03 Variance |
Approved plan for cooperative federal/provincial
relationship to guide joint reviews |
In progress |
Complete |
Complete |
— |