 |
 |
2002/03 Annual Service
Plan Report
Environmental Assessment Office |
 |
 |
Year-at-a-Glance Highlights
Overview
In fiscal 2002/2003 major changes were made to the environmental
assessment review process. British Columbia's Environmental Assessment
Act (R.S.B.C. 1996, c.119) which had been in effect since June,
1995 was replaced with a new Environmental Assessment Act
(S.B.C. 2002, c. 43). There were a number of strengths to the original
environmental assessment process; it was thorough, balanced, integrated,
open and participatory. However, over the years, a number of limitations
were found with the legislation, in particular, the process was
highly prescriptive and standardized rather than flexible to deal
with the challenges of individual project reviews.
Environmental Assessment Reform and Transition
In response to the government's commitment to more flexible, efficient
and timely reviews of proposed major projects to help revitalize
the economy, the Environmental Assessment Office undertook a major
reform of the environmental assessment process resulting in the
new legislation. On December 30, 2002, the new Environmental
Assessment Act (S.B.C. 2002, c. 43) (the Act) was proclaimed.
The primary objective of the new legislation is to provide greater
flexibility to customize review procedures on a project-by-project
basis. The increased flexibility is intended to contribute to the
government's strategic priorities for an improved investment climate
while preserving high environmental standards. Additional objectives
of the legislative reform are clearer process management accountabilities,
increased procedural choice, greater certainty and credibility for
proponents, reduced agency workloads and government program delivery
costs, and improved federal/provincial harmonization.
Accompanying the new legislation were new and updated regulations,
including the: Reviewable Project Regulation (BC Reg. 370/2002);
Concurrent Approval Regulation (BC Reg. 371/2002);
Transition Regulation (BC Reg. 374/2002); Prescribed Time
Limits Regulation (BC Reg. 372/2002), and the new Public
Consultation Policy Regulation (BC Reg. 373/2002)
that provides assurances for consultation within every project review.
To facilitate implementation of the new legislation and transition
to the new process, the Environmental Assessment Office:
- Developed Transition Orders so that all projects under review
could be continued under the new process;
- Published a "Guide to the British Columbia Environmental Assessment
Review Process," a comprehensive overview of the new Act and regulations,
including guidelines for public and First Nations consultation.
The Guide and a summary brochure describing the review process
are available on the Environmental Assessment Office website at:
http://www.eao.gov.bc.ca;
- Implemented a new organizational plan and structure for the
Environmental Assessment Office that met budgetary targets, decreased
the number of Environmental Assessment Directors and created new
Project Assessment Manager and Project Assessment Officer positions;
- Restructured the previous Project Registry into a Project Information
Centre that provides electronic access to extensive project review
documentation; and
- Completed an interim extension to the Canada-British Columbia
Agreement on Environmental Assessment Cooperation.
Projects
During the 2002/03 fiscal year, the Environmental Assessment Office
completed environmental assessments of six major project proposals,
which subsequently obtained certification. Of the six projects,
all were certified under the former Act except for the Forrest Kerr
Hydroelectric Project which was certified under the new Act.
Silverberry Secure Landfill Project
(Canadian Crude Separators Inc.)
In March 2002, Canadian Crude Separators Inc. applied for approval
to build and operate the Silverberry Secure Landfill approximately
50 kilometres north of Fort St. John to store special wastes from
the oil and gas industry. This $32 million secure landfill facility,
which would be the first facility of its kind in British Columbia,
was approved on July 10, 2002. Construction of the secure landfill
was initiated later in 2002.
Burnaby Lake Rejuvenation Project
(City of Burnaby)
In May 2002, the City of Burnaby submitted an application for federal
and provincial approval to rejuvenate Burnaby Lake through a dredging
program involving the removal of up to approximately 400,000 cubic
meters of sediment over an area of about 36 hectares. The full-scale
dredging program would cost $29 million and result in 86 person
years of employment. The dredging program will improve environmental
conditions by removing sediments that have high levels of contamination
from point and non-point sources. The program will also reduce
some noxious weeds currently growing in the lake. By deepening the
water, conditions at the mouths of creeks will be improved for fish
and the resulting open water will allow the re-establishment of
a standard rowing course. Project approval certification was granted
in September 2002.
Stewart Bulk Terminals Wharf Expansion Project
(Stewart Bulk Terminals Ltd.)
On July 2, 2002, Stewart Bulk Terminals Ltd. submitted an application
to undertake a $6 million expansion of its bulk storage and
loading marine terminal operating capacity near the town of Stewart
by constructing a new wharf and facilities to service barges and
cargo at all stages of the tide. Project approval certification
was granted in October 2002. The company has designed the project
to avoid harm to key salmon habitat and will develop operating procedures
to protect against accidents and malfunctions. Project construction
has not yet begun.
Basal Aquifer Dewatering Project
(Highland Valley Copper Corporation)
On February 19, 2002, Highland Valley Copper Corporation submitted
an application for the Basal Aquifer Dewatering Project. The proponent
proposes to increase extraction of groundwater surrounding the mine's
existing Valley Pit and to discharge this water to nearby Witches
Brook to enable the extension of the life of the mine. The project
received certification in August 2002. It was determined that any
potential environmental impacts could be adequately mitigated by
measures to govern the discharge of water to meet the needs of downstream
aquatic resources and mine operations. A multi stakeholder monitoring
committee will oversee a proponent monitoring program to ensure
the environment is protected. Extending mine life by 3.5 years prolongs
the social and economic benefits of the existing mine, such as $450
million in annual company expenditures in B.C. and 950 existing
jobs which represent $82 million in annual employee wages and benefits.
Forrest Kerr Hydroelectric Project
(Coast Mountain Hydro Corporation)
In June 2002, Coast Mountain Hydro Corporation submitted an application
for federal and provincial approval to construct and operate the
Forrest Kerr Hydroelectric Project. This $193 million project
includes a new 100 megawatt power plant at the confluence of the
Forrest Kerr Creek and the Iskut River, located approximately 100
kilometers northwest of the town of Stewart, as well as a 188 km.
DC transmission line with converter stations, from the plant site
to Meziadin Junction. The Project was certified in March 2003 with
conditions that ensure sufficient water flow to avoid adverse fish
impacts. The project will generate approximately 130 person-years
of employment during the 2-3 year construction period as well as
4 full-time and 4 part-time operating jobs. A comprehensive Environmental
Management Plan will guide project construction and operation.
Tulsequah Chief Mine Project
(Redfern Resources Ltd)
The Tulsequah Chief Mine Project, located in northwestern British
Columbia, was approved in March 1998 following a three and a half
year environmental assessment review. The Taku River Tlingit First
Nation had concerns about the approval and sought a judicial review,
which resulted in the project approval certificate being quashed
by the British Columbia Supreme Court.
On January 31, 2002, the British Columbia Court of Appeal ruled
that the proposal for the Tulsequah Chief Mine project should be
remitted directly to the Ministers for decision. On December
12, 2002 the Minister of Sustainable Resource Management and the
Minister of Energy and Mines approved the project following extensive
First Nations consultation which included meetings with ministers
and the Taku River Tlingit First Nation. The ministers have concluded
that all key environmental issues with the project have been resolved
through process or are resolvable by means of an ongoing adaptive
management process.
Amended Certificates and Projects Under Review
In addition to those reviews completed during the 2002/03 fiscal
year, 27 projects were in various stages of the environmental assessment
process (Appendix 2). Also, 4 existing project approval certificates
were amended (Appendix 1).

Intergovernmental
Federal-Provincial Harmonization
In October 2002, the governments of Canada and British Columbia
approved an interim extension to the 1997 agreement on environmental
assessment cooperation. The interim extension will remain in force
until a long-term agreement can be negotiated that reflects the
amendments proposed for the Canadian Environmental Assessment
Act in Bill C-9 which is expected to come into force later this
year. The 1997 agreement was successful in ensuring that the environmental
effects of proposed projects are carefully considered in joint reviews
while respecting the decision making responsibilities of both levels
of government. Amendments included in the extension improve and
update the 1997 agreement by:
- Providing greater flexibility in establishing a basis for a
common environmental assessment report;
- Establishing a dispute resolution mechanism; and
- Making provision for project specific work plans to avoid duplication,
overlap, and improve timeliness of reviews
In preliminary discussions with the Canadian Environmental Assessment
Agency, staff have begun to craft a new long term agreement. Issues
raised during the interim agreement consultations will be carefully
revisited. The public will have an opportunity to comment on a new
agreement before it is signed.
British Columbia — Washington State
The Environmental Assessment Office signed a memorandum of understanding
with the Washington Department of Ecology regarding cooperation
on environmental assessment in June 2001. The purpose of the protocol
is to ensure that each jurisdiction provides notice of and information
about projects that are within 100 km. of the international
border and therefore could have effects on the neighbouring jurisdiction.
The Environmental Assessment Office invited the Department of Ecology
to participate in the review of the Vancouver Island Generation
Project near Nanaimo and the Inland Pacific Connector Project, a
proposed pipeline that would extend from Oliver to Huntingdon, B.C.
In addition, Washington State agencies continued to actively participate
in the Cascade Heritage Power Plant Park Project on the Kettle River,
two kilometers south of Christina Lake in the Regional District
of Kootenay Boundary.
The Environmental Assessment Office has received notice about projects
with which the Department of Ecology has direct involvement in Washington
State, but to date British Columbia has determined it has no
interest in these projects because they have low potential for impacts
in B.C. The notice and information provisions do not extend to projects
covered by the Washington State Energy Facility Site Evaluation
Council.
Electronic Project Information Centre
An initiative critical for the success of the reformed environmental
assessment process is the use of new technology for electronic service
delivery. The electronic Project Information Centre (ePIC, also
called the e-Registry) is the primary means for web-based access
to environmental assessment information, including terms of reference
for project applications, project applications, public notices,
orders, public and government comments, assessment reports, ministers'
certification decisions and other documents. The ePIC is essential
for efficient and effective environmental assessment and for ensuring
open government and accountable decision-making.
The ePIC was implemented in January 2003. The Environmental Assessment
Office will monitor the effectiveness of the ePIC and develop system
updates and enhancements as necessary. In early 2003, considerable
progress was made towards the development of a review participant
contact management module, as well as an internet mapping application
to allow users to search for projects geographically. The Environmental
Assessment Office will continue to rely on the Chief Information
Office and the Ministry of Sustainable Resource Management for leadership
in the area of standards for electronic service delivery, records
management, and the protection of information and privacy.
Certification Compliance
The Environmental Assessment Act does not require the Environmental
Assessment Office to monitor proponent compliance with certification
conditions. Certification conditions are usually associated with
statutory permitting and other programming interests of one or more
line agencies and the Environmental Assessment Office relies on
the line agencies to track compliance with certificate conditions.
In fiscal year 2001/02, the Environmental Assessment Office examined
the effectiveness of this approach by initiating a certification
compliance review for three previously certified projects.
Further work was undertaken for the certificate compliance review
of the Kemess South mine project during 2002/03, and by March 31,
2003, an advanced draft of the final report had been prepared. It
is anticipated that the report will be finalized during the summer
of 2003.
|