Goals, Objectives, Strategies and Results — Continued
Goal 1: Efficient and Effective Delivery of Environmental
Assessment.
This goal will be met through two objectives — continual
improvement of provincial environmental assessment and greater procedural
certainty when both the provincial and federal review processes
are triggered.
- Objective 1:
- Continual Improvement of Provincial Environmental Assessment.
Improvements to environmental assessment are ongoing. Most recently,
reforms to the BC Environmental Assessment Act have streamlined
and improved the process by making it less prescriptive and more
flexible. The strategies set out below address areas of the process
to focus improvements.
Performance Measures |
2003/04 Actual/Base |
2004/05 Target |
2005/06 Target |
2006/07 Target |
Duration of government application review. |
Base data collection in progress. |
90% of application reviews completed in 180 days. |
Maintain or improve. |
Maintain or improve. |
Proponents' level of satisfaction with the review process1.
• EA review is focused on key issues
• Mitigation measures canvassed and applied
• EA Report to the Minister is fair and balanced
|
Develop methodology and undertake survey to determine baseline.
|
Continual process improvement based on feedback from proponents
and identification of key issues. |
Continual process improvement based on feedback from proponents
and identification of key issues. |
Continual process improvement based on feedback from proponents
and identification of key issues. |
Average annual2 EAO costs per project for environmental
assessment. |
The average annual project cost for 2003/04 is $106,000
which is down from $131,000 in 2002/033. |
Maintain or reduce. |
Maintain or reduce. |
Maintain or reduce. |
Deregulation: reducing unnecessary red tape and regulation. |
56% reduction in regulatory requirements of provincial environmental
assessment. |
Maintain or reduce regulatory requirements of provincial
environmental assessment. |
Maintain or reduce regulatory requirements of provincial
environmental assessment. |
Maintain or reduce regulatory requirements of provincial
environmental assessment. |
Stage of Enterprise Wide Risk Management4 Implementation. |
Risk Management assessment is intuitive and ad hoc. |
Formal risk management assessment applied to key EAO strategies.
|
Formal risk management assessment updated. Identified risks
are proactively managed. |
Risk management is strongly integrated with EAO management
practices. |
- Strategies:
- 1. Deliver a timely and cost-efficient provincial environmental
assessment process.
- 2. Evaluate the environmental assessment process, and refine
based on implementation experience.
- 3. Align environmental assessment and permitting/licensing.
- 4. Fulfill government's legal obligations towards First Nations.
- 5. Apply Enterprise-Wide Risk Management (ERM) to Environmental
Assessment Office key strategies by implementing ERM program activities.
- Objective 2:
- Enhance federal/provincial cooperation to increase timeliness
and certainty, and minimize overlap and duplication.
When a project is subject to both the Canadian Environmental
Assessment Act as well as the British Columbia Environmental
Assessment Act, the Environmental Assessment Office works closely
with the Canadian Environmental Assessment Agency (CEAA) and other
federal agencies to ensure the requirements of both levels of government
are met through a harmonized process. Under the Canada/British Columbia
Agreement for Environmental Assessment Cooperation, the requirements
of both processes are met through coordinated assessments to minimize
duplication and overlap. Work plans, signed off by the Environmental
Assessment Office and CEAA, are developed for each project requiring
a harmonized review. They set out the project-specific procedures
for completing a harmonized review, which includes scope of project,
scope of assessment and project review schedule.
Performance Measure |
2003/04 Actual/Base |
2004/05 Target |
2005/06 Target |
2006/07 Target |
Per cent of harmonized reviews that meet provincial timelines1. |
Finalize new Canada/BC Agreement on Environmental Assessment
Cooperation. |
80% of all harmonized reviews meet provincial timelines. |
Maintain or improve. |
Maintain or improve. |
- Strategies:
- 1. Early consultation with CEAA and federal agencies and
proponents on projects entering the process.
- 2. Develop and implement operational procedures for work
plans to facilitate federal/provincial harmonization.
- 3. Maintain the CEAA/Environmental Assessment Office Harmonization
Working Group to address federal/provincial coordination issues.
|